The First Trial of Genergy's New Testing Equipments

  To make sure the new equipments will perform well, Genergy has successfull inspected the products for the first time on Aug.14, 2015,Ganzhou. The detailed procedure record is as below:


First, the batteries will be connected together with our inspection equipments and discharged by 3 times' capacity.

Second, after 7 minutes, check batteries' voltage. Any battery with voltage less than 9.6 volt will be picked out to the Defects Area.

Third, check the consistency.

Last, charge the battery.


All the data regarding batteries’ charging and discharging will be shown through the real-time data monitorning sysytem. A dedicated staff will keep monitoring the real-time data during the whole inspection.